Starting up of the two-phase project of slag bowls production organization
The project started on 01.01.2022

The contract with the customer provided for the delivery and start up of equipment in two phases.
The first phase
Started up in 2022 and consisted of the following equipment:
- Mobile mixer with a capacity of 60/20 t/h (with a capacity of 60 t/h for silica sand and 20 t/h for chromite sand);
- Shake out grid 3500×7000 mm complete with a lump crusher, magnetic separator, cooler/classifier and filtration unit;
- Thermal reclamation plant with a capacity of 3 t/h;
- Pneumatic transport system.
The second phase
Started up in 2023 and consisted of the following equipment:
- Stationary mixer of lifting type with a capacity of 80 t/h;
- Stationary mixer with a capacity of 10 t/h and vibrating table for the production of cores;
- Dynamic reclamation plant with a capacity of 20 t/h;
- Shake out grid 6000×7000 mm complete with a lump crusher, magnetic separator, cooler/classifier and filtration unit.
The start up of new equipment allowed the customer to double the production volumes.