Launch of three automatic die casting complexes for casting lamp housings in central Russia

The project started on 01.11.2021

BLG project 001 копия

In order to expand production, three YIZUMI die casting complexes with locking force of 1,000, 1,250 and 1,650 tons were purchased.

The supplied die casting complexes are capable of producing castings weighing more than 10 kg and are equipped with a full range of peripheral devices. The design capacity of the plant has been increased to 2,000,000 pieces of finished products per year.

Main characteristics of foundry complexes:

  • Locking force — 1,000, 1,200, 1,650 tons;
  • Cycle time from the moment of melt feeding to placing the casting on the finished product conveyor — 45 seconds;
  • Capacity of one complex — not less than 3,000 castings per day;
  • Fully automated process with the use of two industrial robots KUKA on one complex.

To date, the company’s products are widely represented in different regions of Russia, as well as sold in Eastern Europe, Africa, Asia (for example, in India) and post-Soviet countries.